HomeMy WebLinkAboutResolution 2021 (14)Resolution No. 14 (2021)
5T. C ROIX Z .UNTY RESOLUTION APPROVING TEXT AMENDMENTS TO THE TOWN OF
HUDSON ZONING ORDINANCE CHAPTER 105-12, COMMERCIAL
DISTRICT; 105-13, INDUSTRIAL DISTRICT; 105-14,
COMMERCIAL/LIGHT INDUSTRIAL DISTRICT; 105-14.1 PLANNED
UNIT DEVELOPMENT DISTRICT
COVER MEMO
TO: County Board of Supervisors
FROM: Ken Witt, County Administrator
Ellen Denzer, Director, Community Development
DATE: April 6, 2021
AGENDA ITEM: Resolution Approving Text Amendments to the Town of Hudson Zoning
Ordinance Chapter 105-12, Commercial District; 105-13, Industrial District;
105-14, Commercial/Light Industrial District; 105-14.1 Planned Unit
Development District
BACKGROUND INFORMATION
Wisconsin Statute 60.62(3) requires that counties review and approve all amendments to town
zoning ordinance text and maps prior to the amendment taking effect. The Town of Hudson,
which has a town zoning ordinance, has approved text amendments that require County Board
approval.
In summary, the text amendments to the Town of Hudson Zoning Ordinance would require site
plans within designated zoning districts to be submitted to the Town at least 15 days in advance
of a Town Plan Commission or Town Board meeting at which the applicant is seeking
consideration and/or approval. The current zoning code requires site plan submittals at least 10
days in advance of a Town Plan Commission or Town Board meeting.
Resolution No. 14 (2021)
5T. C Rqi UNTY RESOLUTION APPROVING TEXT AMENDMENTS TO THE TOWN OF
HUDSON ZONING ORDINANCE CHAPTER 105-12, COMMERCIAL
DISTRICT; 105-13, INDUSTRIAL DISTRICT; 105-14,
COMMERCIAL/LIGHT INDUSTRIAL DISTRICT; 105-14.1 PLANNED
UNIT DEVELOPMENT DISTRICT
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
WHEREAS, on February 2, 2021 the Town of Hudson Town Board held a properly
noticed public hearing on the proposed text amendments to the Town of Hudson Zoning
Ordinance; and
WHEREAS, following the public hearing, the Hudson Town Board approved text
amendments shown in Exhibit A; and
WHEREAS, Wis. Stat. § 60.62(3) states that in counties having a county zoning
ordinance no town ordinance amendment is effective unless approved by the county board; and
WHEREAS, St. Croix County has a zoning ordinance; and
WHEREAS, the Community Development Committee has reviewed the proposed
amendment and recommends approval.
NOW, THEREFORE, BE IT RESOLVED by the St. Croix County Board of
Supervisors that the amendments to the Town of Troy Zoning Ordinance described above are
hereby approved.
Leqal - Fiscal- Administrative Approvals:
Legal Note:
Fiscal Impact:
r/A X 70
.•
K_ V ^�` min 3/12J2021
03/18/21 Community Development Committee RECOMMENDED
RESULT:
RECOMMENDED [UNANIMOUS]
MOVER:
Ed Schachtner, Vice Chair
SECONDER:
Shawn Anderson, Supervisor
AYES:
Schachtner, Anderson, Counter, Hansen, Achterhof
EXCUSED:
Dick Hesselink
Vote Confirmation.
Dan Hansen CommunhyDe velopmeK Chakman 1
St. Croix County Board of Supervisors Action:
Roll Call - Vote Requirement — Majority of Supervisors Present
RESULT: ADOPTED BY CONSENT VOTE [UNANIMOUS]
MOVER: Dave Ostness, Supervisor
SECONDER: Paulette Anderson, Supervisor
AYES: Schachtner, Anderson, Long, Leaf, Koch, Hall, Berning, Ottino, Feidler, Ostness,
Counter, Hansen, Ard, Tellijohn, Peterson, Anderson, Achterhof, Tomtschik,
Peavey
This Resolution was Adopted by the St. Croix County Board of Supervisors on April 6, 2021
Campbell, County Clerk
EXHIBIT A
That, § 105-12. Commercial District, J. Procedure for site plan approval section as noted be
repealed and replaced with:
J. Procedure for site plan approval.
(1)(a) Copies of the site plan must be submitted to the Town Clerk at least 15 days in advance of
the Town PIan Commission or Town Board's meeting at which the applicant is seeking
consideration and/or approval. In all cases the site plan must be to scale and contain the
minimum:
(,Sections [1] through [30] to remain as is.)
and
That § 1 a5-13. Industrial District. L Procedure for site plan approval section as noted be repealed
and replaced with:
1. Procedure for site plan approval.
(1) Copies of the site plan must be submitted to the Town Clerk at least 15 days iii advance of
the Town Plan Commission or Town Board's meeting at which the applicant is seeking
consideration and/or approval. In all cases the site plan must be to scale and contain the
same information as is required in § 105-12J, Procedure for site plan approval, in the
Commercial District.
and
That § 105-14 Commercial/Light Industrial District, I. Procedure for site plan approval section as
noted be repealed and replaced with:
I. Procedure for site plan approval.
(2) Section 105-12J(1)(a) through (g), (2), (3), (4) and (5), of the Commercial District of this
Zoning Ordinance applies.
and
That § 1 Q5-14.1 Planned Unit Development District. I Application process section as noted be
repealed and replaced with;
(1) Site plan. Site plan approval must first be granted by the Plan Commission and then the
Town Board prior to any permit being issued and construction commencing, Copies of the
site plan with the date prepared and certified by a registered professional engineer for the
State of Wisconsin must be submitted to the Town Cleric at least 15 days in advance of the
Plan Commission or Town Board meeting at which the applicant is seeking approval. The
site plan shall be to scale and provide the following information:
(Sections (a) through (g) to remain as is.)
(2) Preliminary development plan. Copies of the development plan with the date prepared must
be submitted to the Town Clerk at least 15 days in advance of the Plan Commission or Town
Board meeting at which the applicant is seeking approval. The development plan shall be to
scale and provide the following information:
(Sections (a) through 0) to remain as is.)