ST. CROIX COUNTY
NOTICE OF COMMITTEE MEETING
TO: Chairman Buck Malick
St. Croix County Board
FROM: Esther Wentz, Chair
COMMITTEE TITLE: Huber Facility Building Committee
DATE: Wednesday, December 17, 2003 10:00 A.M.
LOCATION: Community Room, Government Center, Hudson
CALL TO ORDER
ROLL CALL
ADOPTION OF AGENDA
DATE OF NEXT MEETING: December 31, 2003
ACTION ON PREVIOUS MINUTES: December 3, 2003
UNFINISHED BUSINESS:
NEW BUSINESS:
1. A Quorum of the Committee Will Be Attending the Bi-Weekly Construction Meeting
2. Review Windows Situation
3. Review Sewer Line and Manhole Work
4. Payment Request No. 5
CORRESPONDENCE:
ADJOURNMENT (Agenda not necessarily presented in this order)
COPIES TO: County Board Office News Media/Notice Board
County Clerk County Board
County Departments
* *ADDITIONS/CHANGES/CORRECTIONS
Last Updated. 1211512003
MINUTES
HUBER BUILDING COMMITTEE
1 00
CALL TO ORDER - Chair Wentz called the meeting to order at io:oo a.m.
IROLL CALL - Wentz, Gunderson, Erickson
V
Also in attendance: Whiting, Best, Robole, Hillstead, Larson, Humphrey, and
Thompkins
I
Hudson City Building Inspector Dennis Christenson
1
(ACTION ON PREVIOUS MINUTES: December 3, 2003
s i
Motion by Gunderson, second by Erickson to approve the minutes of the December 3, 20031
`meetings. Motion passed unanimously.
I
INEW BUSINESS:
1. Bi-weekly construction meeting. Donna Rodgers from Dell opened the meeting.
Several sub-contractors were present and reviewed the project status. She stated
she has received word that the windows can be delivered at the end of January.
Window installation should take about four days. Larson noted he had called the
window manufacturer as well. A plumbing issue was reviewed with the City
Building Inspector. Valve changes by the contractor will be necessary in order to
meet City code. The cost will be at the contractor's expense and take a day or two.
f
i2. Review Sewer Line and Manhole Work. The Committee reviewed the
circumstances that led to the additional cost for sewer and manhole work early in
the project. The problem centered on the project drawings having not been based j
on the as-built drawings for the Government Center, and therefore connections
were not in the places they were expected to be. The additional costs were likely
costs the County would have incurred regardless if the correct locations had been
used in the design of the Huber expansion. It is unclear as to whether the cost
would have been different had the plans been correct to begin. The Committee
reviewed project costs to date that are very close to expected costs and saw no
reason to review this concern further.
i`
13. Payment Request No. 5: This has been submitted and reviewed by Ayres. I
4 Motion to approve Payment Request No. 5 made by Erickson, seconded by
} Gunderson. Motion passed unanimously.
14. Next Meeting - December 31, 2003 Construction meeting.
Respectfully submitted,
Chuck Whiting
Administrative Coordinator