HomeMy WebLinkAboutResolution 1992 (56) RESOLUTION NO. „,VD (-
COUNTY AID CONSTRUCTION AND MAINTENANCE
DURING THE CALENDAR YEAR 1993
SECTION I. The County Board of Supervisors of St. Croix County,
Wisconsin, regularly assembled, does hereby ordain that such funds as may
be made available to the county for highway work in the year 1993 under
the provisions of Section 20.395 and Chapter 86 of the Statutes, and the
additional sums herein appropriated, shall be expended as hereinafter set
forth:
SECTION II. COUNTY TRUNK HIGHWAY ALLOTMENT: WHEREAS, the Division of
Highways has notified the County Clerk that sum of money estimated to be
eight hundred thirty thousand dollars ($830,000.00) will be available at
the end of the fiscal year under the provisions of Sections 86.30 and
20.935 of the Statutes, for the county trunk highway system in the
county, but the actual amount will not be known until the close of the
fiscal year ending June 30, 1993.
NOW, THEREFORE, BE IT RESOLVED that the County Highway Committee is
authorized and directed to expend the said sum to the extent required to
match and supplement Federal aid for construction, right of way, and
other costs on any Federal projects located on the county trunk highway
system of said county, which are not recovered from Federal funds, and to
expend any balance for constructing, repairing and maintaining such
county trunk highway system and the bridges thereon, including snow and
ice removal and control, as directed in Section 86.30 (7) of the
Statutes, and to reimburse the general fund for any expenditures that may
be made therefrom pursuant to Section 83.01 (6) of the Statutes. The
distribution to such purposes is estimated, but not specifically
directed, to be as follows:
SECTION III. WHEREAS, it appears that certain additional highway
improvements in the county are necessary and warranted.
NOW, THEREFORE, BE IT RESOLVED that the County Board does hereby
appropriate the following sums for the purpose hereinafter set forth:
(1) The sum of three hundred thirty one thousand two hundred dollars
($331,200.00) to match Federal Funds for construction on the County Trunk
Highway System, to be used toward the following projects as far as funds
will permit:
CTH ESTIMATED CO.
PROJECT LENGTH TYPE OF IMPROVEMENT SHARE
1. 90 -C -1 2.40 miles Complete construction $ 0.00
2. 93 -I -1 2.25 miles Complete construction 116,000.00
3. 93 -H -1 2.00 miles Spot improve & overlay 44,000.00
4. 93 -E &T -1 Bridge Replacement 38,000.00
5. 93 -M -1 (HH) Bridge Deck replacement 11,200.00
6. 93 -Y -1 Bridge Deck replace & substructure 116,000.00
7. Safety RR Crossings Safety enhancement projects 6,000.00
(2) The sum of two hundred twenty five thousand dollars ($225,000.00)
for construction on the County Trunk Highway System toward the following
projects as far as funds will permit:
CTH ESTIMATED CO.
PROJECT LENGTH TYPE OF IMPROVEMENT SHARE
1. 92 -N -1 1.75 miles Project completion $ 0.00
2. 93 -D -1 1.25 miles Project completion 140,000.00
3. Engineering Future projects 85,000.00
(3) For the maintenance of the County Trunk Highway System, the sum
of one million five hundred and nine thousand dollars ($1,509,000.00).
(4) For administration, including Highway Department- sa.14J ies, office
and travel expense, the County Highway Commissioner,. clerks and
assistants not paid from construction ors09taintenance fun ; the sum of
three hundred thirty three thousand one hed dollars ($3,,100.00).