Loading...
HomeMy WebLinkAbout016-1047-60-000(4) CROIX COUNI m PLANNING & ZONING e January 30, 2013 File LU87755 Signal Acquisition, LLC _z John Knapek 18285 Imagery Lane Lakeville MN 55044 5 Re: Land use permit for a Sprint Tower co-location on an existing tower at 1408 300`n ty_ Street, Glenwood City WI 54013. Parcel # 016-1047-20-000 Code AdmL2&&22~on 715-386-4680 1 Dear Mr. Knapek: I Laced Information ;J This letter confirms zoning approval according to the plans you have submitted to the P 715386-4674 Planning and Zoning Department to replace and add telecommunications equipment on an existing wireless communication tower located on property listed above. Staff finds that the Real Properly project meets the applicable tower provisions in Sections 17.82 17.85, 17.86, and 17.87, of the 715-38(4677 St. Croix County Zoning Ordinance based on the following findings: Re_1 li 1. Approval of this land use permit includes the replacement and addition of 7-15-386-4675 tt; telecommunications equipment on a 290 foot existing American Tower. A list of these replacements and additions is on the page 2 of both of the -structural analysis report, dated August 24, 2012. The report shows that the tower will support the added equipment. =z. 2. The installation plans were prepared by Wm. E. Garrett, a professional engineer. r 3. A copy of the lease has been submitted. 4. A certificate of liability of insurance has been submitted. 5. This is the only tower located on this property. 6. Co locating on a tower is a permitted with a land use permit in the Agricultural Zoning x District. 7. A letter from David Kirk a Radio Frequency Engineer has been submitted verifying this facility will not cause interference with public safety communication systems. This permit has been issued to Sprint with the following conditions; W 1. The applicant shall contact the Planning and Zoning Department at least five days " prior to commencing installation of the proposed antennae and equipment. 2. The applicant shall inform the Zoning Administrator when construction is complete and submit photos of the completed antennae and equipment. ts3 3. The applicant shall have one (1) year from the issuance of this land use permit to complete construction. If the permit expires, the applicant will be required to secure a new land use permit. 4. The applicant shall notify the Zoning Administrator of any change in name or ownership of the approved facilities and provide new contact information for the V-A purpose of keeping the file updated. ST. CROIX COUNTY GOVERNMENT CENTER 715386.4686 Fitz PZCaCO.5,41NT-CR0IX.W.US 1101 CARM/CHAELROAD, HUDSON, W1 54016 WWW.CO.SAIMCROIX.VA.US i 5. Any minor change (or addition) in the project shall require prior review and approval by the Zoning Administrator. Any major change and/or addition to the originally approved plans will require the submittal of a new land use permit application. 6. Within 12 months of cessation of operation or use of the wireless facilities, all unused antennas and equipment shall be removed at the applicant's expense. After the facilities are removed, the site shall be restored to its original condition or an improved condition. This approval does not allow for any structures (temporary or permanent), activities, or development beyond the limits of this request. Your information will remain on file in the St. Croix County Planning and Zoning Department. Please contact the Town of Gelenwood to obtain the necessary building permits for the proposed construction. It is your responsibility to ensure compliance with any other local, state, or federal rules or regulations. Pleas call if you have any questions. Sincerely, Ax Alex Blackburn Land Use and Conservation Specialist cc: Thomas and Linda Weber, 1408 300'h Street, Glenwood City WI 54013 Clerk, Town of Glenwood Enc: Land Use Permit LU87755