April 4, 2005 File 30-03
Mark and Kathleen Buechel
404 Orange Street
Prescott, WI 54021
Re: St. Croix County Special Exception Permit
Parcel#: 25.29.19.2442, Town of Hudson
Dear Mr. and Mrs. Buechel,
This letter confirms that you have met all of the conditions of your special exception permit
approved by the St. Croix County Board of Adjustment on August 28, 2003. Within the last
month, I have received from you copies of the following outstanding items:
• Oak Savanna Restoration Plan, recorded against the deed for the property.
• Stormwater management plan and drainage easement for the permanent storm water
control structures recorded against the deed for the property.
Thank you for your cooperation in meeting the conditions of your permit. If you have any
questions or concerns, please feel free to contact me at 715-386-4680.
Sincerely,
Jenny hillcox � e
Zoning Specialist
Cc: Pete Kling, St. Croix County Land and Water Conservation Department
Rita Horne, Town of Hudson
ST. COW COUNTY
WISCONSIN
ZONING OFFICE
F rrrrrrrrr - .....
ST. CROIX COUNTY GOVERNMENT CENTER
1101 Carmichael Road
-`—� Hudson, WI 54016-7710
(715) 386-4680 r Fax (715) 386-4686
October 2, 2003 File Ref: 30-03
Mark T and Kathleen A. Buechel
404 Orange Street
Prescott, WI 54021
Re: Board of Adjustment Decision
Dear Mr. and Mrs. Buechel:
The St. Croix County Board of Adjustment has reviewed your request for a special exception for a
permit for filling and grading in excess of 1,000 square feet on slopes between 12-20% in a
Shoreland District and has approved this application with conditions. The enclosed document is the
formal decision regarding your application.
Should you have any questions or concerns,please do not hesitate in contacting me.
i Sincerel
Steve Fisher
Zoning Director
dz
Enclosure
cc: Matt Hieb, ACA, w/enclosure
Rita Horne, Clerk,Town of Hudson,w/enclosures
Pete Kling,LWCD,w/enclosures
DNR,w/enclosures
submitted in favor of St. Croix County, to be held by the Zoning Office for the erosion
control and grading activities(to ensure proper construction). The initial financial
guarantee period shall be for a minimum of one year and shall automatically renew until
the county releases any or all of the financial guarantee
• Written estimates must be submitted to the Zoning office for review and approval.
• No construction, including earth moving, shall take place prior to approval of the
financial guarantees
• The applicant shall have the engineer submit proof that the plans were installed as
approved. This document can be submitted in the form of an as-built or other
document that county staff can review to ensure the plans were installed in
accordance with the original design.
• Upon substantial completion of all required improvements, the applicant shall notify
the County Zoning Administrator of the completion of the improvements in writing.
The County Zoning Administrator, in consultation with appropriate experts, shall
inspect the improvements.
• The County may retain a portion of the guarantee, for a period not to exceed two
years after final acceptance of an improvement to ensure the project has been
stabilized, this amount is not to exceed 15%of the cost of the improvement(erosion
control and grading activities).
4. The applicant must record a storm water management plan and a drainage easement for
the permanent storm water control structures against the deed for the property. The
applicant is responsible to provide a recorded copy to the Zoning Office. The intent is to
make the current and future owners aware of the responsibilities associated with the
storm water management plan as well as the limitations (filling, grading, etc.) the
landowner incurs as a result of the plan.
5. The applicant is to submit an Oak Savanna Restoration Plan for County review and
approval. This information will be placed on a deed, restricting this area to remain as is.
6. Prior to beginning any work,the applicant must schedule an on-site pre-construction
meeting that includes the landowner, contractor, engineer, architect, and St. Croix County
Zoning and LWCD staff members. Items to be discussed include but are not limited to
coordinating installation of BMP's, construction timelines,roles and responsibilities of
owner, engineer, architect, contractor, etc.
7. The applicant shall provide the Zoning Office with the name and phone number of the
person responsible for installing and maintaining the erosion control plan.
8. The applicant shall obtain all necessary approvals from the Wisconsin Department of
Natural Resources.
9. The applicant must secure a township building permit before commencing construction.
10. The Zoning office is to be notified at the start and the finish of the project.
11. Any minor change or addition to the project, including but not limited to design of the
project, shall require review and approval by the Zoning Administrator and the Land and
Water Conservation Department prior to making the change or addition. Any major
change or addition to the originally approved plan will have to go through the special
2
exception approval process.
12. The applicant shall have one(1) year from the issuance of the special exception permit to
commence construction. Failure to do so shall result in revocation of the special
exception permit. If the special exception permit expires before construction commences,
the applicant will be required to secure a new special exception permit before starting or
completing construction on the project.
13. These conditions may be amended or additional conditions may be added if unanticipated
conditions arise that would affect the health and/or safety of citizens or degrade the
natural resources of St. Croix County. Conditions will not be amended or added without
notice to the applicant and an opportunity for a hearing.
14. Accepting this decision means that the applicant has read,understands, and agrees to all
conditions of this decision.
The following vote was taken to approve: Krueger, yes; Marzolf, yes; Peterson, yes; Golz, yes;
Chairperson Speer, yes. Motion carried.
APPEAL RIGHTS
Any person aggrieved by this decision may file an appeal in St. Croix County circuit court within
30 days after the filing date shown below,pursuant to sec. 59.694(10),Wisconsin Statutes. St.
Croix County assumes no responsibility for action taken in reliance on this decision prior to the
expiration of the appeal period. St. Croix County does not certify that the identity of all persons
legally entitled to notice of the Board of Adjustment proceedings,which resulted in this decision,
was provided to the County.
If an appeal is taken of this decision, it is the responsibility of the appellant to submit at his/her
expense a transcript of the Board of Adjustment proceedings to the circuit court,which is available
from Northwestern Court Reporters,Hudson,Wisconsin. It is the responsibility of the Board of
Adjustment to submit its record(file)of this matter to the circuit court.
ZONING BOARD OF ADJUSTMENT
Signed:
ha erso
Dated: 10/02/03 Attest:
Filed: 10/02/03 Zoning Director
3